Lofty diversion project kicks off ( 2003-12-30 00:58) (China Daily)
Ground was broken Tuesday in southern Beijing and the neighbouring Hebei
Province to launch into full swing the construction of the long-awaited middle
line of the south-to-north water diversion project.
A sketch map of
the middle line of the south-to-north
project
Work on two inverted siphons, part of
the Beijing-Shijiazhuang section of the middle line, began in Beijing and the
Hutuo River near Shijiazhuang, capital of Hebei Province, a senior official
announced Tuesday.
"The kickoff of the Beijing-Shijiazhuang section was a milestone for
simultaneous construction along the middle and eastern lines of the gigantic
diversion project,'' said Zhang Jiyao, a top official with the office
responsible for the water diversion project under the State Council, at the
Beijing construction site on the Yongding River Tuesday.
"They will bring construction of the two lines (middle and east) into full
swing in the years to come," he added as hundreds of bulldozers began work.
The south-to-north water diversion project consists of three south-to-north
canals each running about 1,300 kilometres across the eastern, middle and
western parts of the country.
Last December, the central government gave the green light for the
construction of the middle and eastern lines of the water diversion project,
China's most ambitious scheme to divert water from the Yangtze River in the
south into the parched north.
In addition to these siphons being built, work on two other sub-projects
related to the line in Shandong and Jiangsu provinces has already begun.
"Work on more sub-projects will follow in other sections along the two lines
early next year," sources with Zhang's office confirmed.
The 307-kilometre long Beijing-Shijiazhuang section is a key part of the
middle line to link four reservoirs in Hebei with Beijing as an emergency water
supply channel to help ease up water shortage for Beijing, according to Jiao
Zhizhong, director of Beijing's municipal water resources office.
"Upon completion, the Beijing-Shijiazhuang section, with an investment of
17.3 billion yuan (US$2 billion), will take 500 million cubic metres of water
per year from the Gangnan, Huangbizhuang, Yukuai and Xidayang reservoirs in
Hebei to Beijing to ensure the capital's security in water supply," Jiao said.
Overall, the south-to-north project is crucial for relieving water shortages,
improving the ecosystem and promoting China's "Go West" strategy, experts say.
Specifically, it would significantly alleviate acute water shortages along
the Yellow River, Huaihe River and Haihe River, eastern Shandong and some areas
in northwestern China, experts predict.
The three lines of the project will divert water from the upper, middle and
lower reaches of the water-rich Yangtze River into the country's drought-prone
north.
The middle line is to take water from the Danjiangkou Reservoir in Central
China's Hubei Province into large cities including Beijing, Tianjin,
Shijiazhuang and Zhengzhou in Henan Province.
The eastern line is designed to transfer water from East China's Jiangsu
Province into Tianjin while hard spadework on the west line continues.
To be built in three stages, the three canals will link up the country's four
major rivers: the Yangtze River, Yellow River, Huaihe River and Haihe River.
Upon its completion scheduled around 2050, the entire project involving
nearly 500 billion yuan (US$60 billion), will deliver 44.8 billion cubic metres
of water into the parched north each year, about the annual volume of water in
the Yellow River, to optimize China's existing water resources for future
sustainability.