Construction on venues for Olympic Games to start ( 2003-12-13 13:31) (China Daily)
Preparations for the
construction of four venues for the 2008 Beijing Olympic Games have been
completed and work is scheduled to start before the end of this month. This
marks the beginning of the three-year Olympic venue construction project.
The first group of venues to be built include the National Stadium, the
National Swimming Centre, the Beijing Shooting Range and the Laoshan Velodrome,
according to sources with the Beijing Organizing Committee for the Games of the
XXIX Olympiad (BOCOG).
Construction of earthwork and infrastructure facilities will be the focus of
the initial work, with actual construction of the venues getting under way next
year, said Ping Yongquan, director of BOCOG's Venue Planning and Construction
Department, who noted that the projects are expected to be completed by 2006.
As the main stadium for the 2008 Games, with an investment of over 3 billion
yuan (US$360 million), the National Stadium will no doubt attract the most
attention among the four venues.
The construction workers and equipment are now ready at the site, which is
located in the Olympic Green, in the north of the city and east of its
north-south axis line, Li Aiqing, chairman of the Beijing State-owned Assets
Management Co Ltd, said in an interview.
Li's company is responsible for the investment, construction and operation of
the National Stadium and the National Swimming Centre.
"The construction site for the stadium has been cleared and the division
lines have been marked. The removal of trees and stumps has been completed. The
electricity supply will be in place before the ground breaking," he said.
So far, the National Stadium Co Ltd, which was jointly established by Li's
company and the China International Trust and Investment Corporation (CITIC)
Consortium, has completed the company registration documents and submitted them
for approval, said sources.
The State-owned assets company has organized four symposiums over the past
months on the steel structure of the National Stadium, the so-called birds'
nest, and on the inner environment of the stadium and the National Swimming
Centre, to invite advice from experts.
"I am so happy to see the active participation of society in construction of
the venues to bring the city the best-ever Olympics," Li said.
As one of the results of the symposiums, a working team organized by Jiang
Yi, an academician of the Chinese Academy of Engineering, is now involved in the
work for the swimming centre.